HVDC Dolwin gamma
Offshore Wind
OVERDICK conducted the overall design, structural design as well as the transport and installation engineering.
2016 June – Jackets installation finalized
OVERDICK News – DOLWIN gamma
2017 July – Topsides installation finalized
OVERDICK News – DOLWIN gamma
- Client
- Nordic Yards2016
- Location
- German North Sea
- Keywords
- Bollard Pull Analysis, FE Analysis, Fixed Platforms, Float over, Calculations, Geotechnical Analyses, Heavy lift engineering, Hydrostatics, In-place analyses, Integrated design solutions, Jacket, MOAB, Motion Analysis, offshore wind, platform, Seafastening, Services, Structural Design
- Characteristics
-
Topsides weight: 18.000 t
Jacket`s weight: 10.000 t
CAT`s weight: 1.100 t
J-Tubes: 12
LAT: 27,5 m
Power: 900 Megawatts
- Engineering Services
-
Concept Design
Foundation Design
Installation Engineering
Transport & Installation Design
Marine Analysis for Tow and Installation
Structural and Basic Engineering
Structural Verification for Transport & Installation - Concept Design
- Foundation Design
- Installation Engineering
- Transport & Installation Design
- Marine Analysis for Tow and Installation
- Structural and Basic Engineering
- Structural Verification for Transport & Installation
- Map
-
- Other Projects in this Category
- MOAB® AC Substation for GLOBAL TE… German North Sea
- Borkum West II - Substation Platform German North Sea
- HVDC Sylwin alpha German North Sea
- MOAB® Helwin alpha German North Sea
- MOAB® Borwin beta German North Sea
- Jack-Up Barge THOR mobile
- MOAB® AC Substation for VEJA MATE… German North Sea
- Heavy Lift Jack-Up Vessel Innovation mobile