MOAB® AC Substation for GLOBAL TECH 1 Wind Park - German North Sea
Offshore Wind
The GLOBAL TECH 1 Substation is a self installing platform according to OVERDICK MOAB® concept.
The entire electrotechnical and utilities equipment it is self-contained within the platform topsides. Included in the topsides is also the hotel module for 40 POB and a full operational helicopter infrastructure.
The GLOBAL TECH 1 MOAB® is a perfect example of the flexibility of the MOAB® concept as a platform for the most various services.
Location: German North Sea
Project Details
- Client
- ALSTOM, 2013
- Keywords
- AC Substation, Collision and Collaps Analyses, FE Analysis, Fixed Platforms, Geotechnical Analyses, Heavy lift engineering, In-place analyses, MOAB, Mooring Analysis, Motion Analysis, offshore wind, platform, Self installable platforms, Structural Design, Towage
- Characteristics
-
Payload: 2.900 t
J Tubes: 16
LAT: 40m
POB: 37
Power: 400MW
- Engineering Services
-
Concept Design
Detail Analysis of Jacket
Detail Engineering
Fabrication Follow-Up
Foundation Design
Heavy Lift Analysis and Design
Installation Engineering
Transport & Installation Engineering
Marine Analysis for Tow and Installation
MetOcean Criteria Definition
Platform Concept
Structural Design
Structural Verification for Transport & Installation