POE GIANT 12 Cranes

Album Preview

POE GIANT 12 Cranes

Salvage and Wreck Removal

OVERDICK engineered the minimal number of cut lines that were required to be made by explosives in order to collapse two bulk unloading cranes away from Horsburgh Lighthouse and into the water.

The finite element model and preliminary results were available within 24 hours of the first call. A final engineering report, required by the Singapore Maritime and Port Authority (MPA) before permission to use explosives would be granted, was issued in less than five calendar days. A faster response was not possible.

The RESOLVE crew worked together with explosives experts to conduct a controlled demolition of cranes onboard the barge POE GIANT 12.

Location: Singapore



Project Details

Client
Resolve, 2015
Keywords
Removal, Salvage
Characteristics

Titel: Wert

Engineering Services

Concept
Structural Analysis